•             24/01/2016         $2000, initial H&L deposit - W
•             27/01/2016         $1000, Initial land deposit
•             31/01/2016         W Changed the package to house only
•             4/02/2016           W Request for new tender
•             7/02/2016           $1000 Initial H deposit & request for M tender
•             15/02/2016         5% Land deposit
•             11/04/2016         $350 W Penalty and request for 2nd tender
•             1/06/2016           Land stamp duty
•             7/06/2016           $4000 Deposit for W builder, cancel M builder
•             24/06/2016         Tiling, Air-con, Kitchen
•             6/07/2016          Wall Unit, Media Entertainment Units
•             8/07/2016           Outdoor and Porch Tiling
•             13/09/2016         Landscape Plan
•             22/09/2016         Air Conditioning Upgrade
•             23/09/2016         Electrical Plan
•             26/09/2016         Post Contract Variations, Balance of 5% Deposit
•             25/09/2016         PA for Full Landscaping Plan
•             21/02/2017         Construction Update
•             26/02/2017         First sight to the land and street
•             15/03/2017         Revised Landscape Quotation
•             16/03/2017         Land ready for valuation
•             17/03/2017         Bank’s conditionally approved
•             27/04/2017         Registered Land
•             19/05/2017         Starting of preparation of council's plan & lodging
•             17/05/2017         We own the lot
•             09/06/2017         Contour Survey Report
•             15/06/2017         Bore Hole Report
•             17/08/2017         Council Development Approval
•             17/08/2017         Construction Certificate
•             25/08/2017         Lender’s Construction Loan Policy Changed (from 5% to 10% deposit)
 
•             27/08/2017         Found the structural error, builder re-apply of construction plan to the Council
•             31/08/2017         1st Blacktown Council Rates and Charges
•             01/09/2017         Final Ground Floor Electrical Plan and Variation completed
•             15/09/2017         1st Electricity and Gas Bills
•             15/09/2017         Section 96 Approved by the Council
•             27/09/2017         Final Colour Selection and Variation Completed
•             29/09/2017         Water Board Approval Sewer Peg Out, $910
•             15/11/2017         Final measure in the Laundry room, received variation but declined payment
•             27/11/2017         Received the final End Panel from builder
•             07/12/2017        Clear the site, no long grass and clean, send photo to the builder
•             16/01/2018         Construction or 2nd Loan Approved!
•             17/01/2018         Day was not good, received new variation charge
•             24/01/2018         Agreed to pay the new variation - $7K contract expiry
•             25/01/2018         Paid additional 5% to the builder to avoid paying LMI to bank
•             30/01/2018         Progress to the Production Estimate Department
•             04/02/2018         Site started!!!
•             07/02/2018         Filling & Excavation!
•             12/02/2018         Additional piering
•             15/02/2018         Piers are done
•             21/02/2018         Slab is ticked
•             06/03/2018         Plumbing & Electrical
•             13/03/2018         External Drainage
•             14/03/2018         Windows delivered
•             27/03/2018         Lower frame 
•             29/03/2018         Upper frame 
•             05/04/2018         Frame completed
•             09/04/2018         Rough-in Plumbing
•             12/04/2018         Bricks Delivery
•             18/04/2018         Half Bricks 
•             25/04/2018         Scaffolding
•             03/05/2018         Bricks cement
•             11/05/2018 Upper-level bricks
•             17/05/2018         Bricks completed
•             24/05/2018         Roof Gutters 
•             28/05/2018         Roof completed
•             09/06/2018         Upper Acid Wash
•             15/06/2018         Rain Delay
•             22/06/2018         Facade Rendering
•             29/06/2018         Lower eaves done
•             06/07/2018         Lower eaves painting
•             13/07/2018         Internal rough in
•             20/07/2018         Speaker wiring
•             24/07/2018         Mixed fill removed
•             01/08/2018         Plasterboard
•             07/08/2018         Sliding doors
•             14/08/2018         Doors, Wet Areas
•             24/08/2018         Tiles, Cement
•             01/09/2018         Kitchen Cabinets
•             07/09/2018         Sinks & Benchtops
•             15/09/2018         Aircon, Electrical,
•             22/09/2018         Water Tank
•             29/09/2018         Robes, Showers
•             05/10/2018         Main floor tiling
•             13/10/2018         Door handles locks
•             17/10/2018         Fence removed
•             26/10/2018         Stairs, Features 
•             03/11/2018         Driveway
•             10/11/2018         L'scaping leveling 
•             14/11/2018         PCI
•             25/11/2018         Paint touch up
•             02/12/2018         Final clean up
•             07/12/2018         OCA
•             14/12/2018         Handover!
•             15/12/2018         Move in!