• 24/01/2016 $2000, initial H&L deposit - W
• 27/01/2016 $1000, Initial land deposit
• 31/01/2016 W Changed the package to house only
• 4/02/2016 W Request for new tender
• 7/02/2016 $1000 Initial H deposit & request for M tender
• 15/02/2016 5% Land deposit
• 11/04/2016 $350 W Penalty and request for 2nd tender
• 1/06/2016 Land stamp duty
• 7/06/2016 $4000 Deposit for W builder, cancel M builder
• 24/06/2016 Tiling, Air-con, Kitchen
• 6/07/2016 Wall Unit, Media Entertainment Units
• 8/07/2016 Outdoor and Porch Tiling
• 13/09/2016 Landscape Plan
• 22/09/2016 Air Conditioning Upgrade
• 23/09/2016 Electrical Plan
• 26/09/2016 Post Contract Variations, Balance of 5% Deposit
• 25/09/2016 PA for Full Landscaping Plan
• 21/02/2017 Construction Update
• 26/02/2017 First sight to the land and street
• 15/03/2017 Revised Landscape Quotation
• 16/03/2017 Land ready for valuation
• 17/03/2017 Bank’s conditionally approved
• 27/04/2017 Registered Land
• 19/05/2017 Starting of preparation of council's plan & lodging
• 17/05/2017 We own the lot
• 09/06/2017 Contour Survey Report
• 15/06/2017 Bore Hole Report
• 17/08/2017 Council Development Approval
• 17/08/2017 Construction Certificate
• 25/08/2017 Lender’s Construction Loan Policy Changed (from 5% to 10% deposit)
• 27/08/2017 Found the structural error, builder re-apply of construction plan to the Council
• 31/08/2017 1st Blacktown Council Rates and Charges
• 01/09/2017 Final Ground Floor Electrical Plan and Variation completed
• 15/09/2017 1st Electricity and Gas Bills
• 15/09/2017 Section 96 Approved by the Council
• 27/09/2017 Final Colour Selection and Variation Completed
• 29/09/2017 Water Board Approval Sewer Peg Out, $910
• 15/11/2017 Final measure in the Laundry room, received variation but declined payment
• 27/11/2017 Received the final End Panel from builder
• 07/12/2017 Clear the site, no long grass and clean, send photo to the builder
• 16/01/2018 Construction or 2nd Loan Approved!
• 17/01/2018 Day was not good, received new variation charge
• 24/01/2018 Agreed to pay the new variation - $7K contract expiry
• 25/01/2018 Paid additional 5% to the builder to avoid paying LMI to bank
• 30/01/2018 Progress to the Production Estimate Department
• 04/02/2018 Site started!!!
• 07/02/2018 Filling & Excavation!
• 12/02/2018 Additional piering
• 15/02/2018 Piers are done
• 21/02/2018 Slab is ticked
• 06/03/2018 Plumbing & Electrical
• 13/03/2018 External Drainage
• 14/03/2018 Windows delivered
• 27/03/2018 Lower frame
• 29/03/2018 Upper frame
• 05/04/2018 Frame completed
• 09/04/2018 Rough-in Plumbing
• 12/04/2018 Bricks Delivery
• 18/04/2018 Half Bricks
• 25/04/2018 Scaffolding
• 03/05/2018 Bricks cement
• 11/05/2018 Upper-level bricks
• 17/05/2018 Bricks completed
• 24/05/2018 Roof Gutters
• 28/05/2018 Roof completed
• 09/06/2018 Upper Acid Wash
• 15/06/2018 Rain Delay
• 22/06/2018 Facade Rendering
• 29/06/2018 Lower eaves done
• 06/07/2018 Lower eaves painting
• 13/07/2018 Internal rough in
• 20/07/2018 Speaker wiring
• 24/07/2018 Mixed fill removed
• 01/08/2018 Plasterboard
• 07/08/2018 Sliding doors
• 14/08/2018 Doors, Wet Areas
• 24/08/2018 Tiles, Cement
• 01/09/2018 Kitchen Cabinets
• 07/09/2018 Sinks & Benchtops
• 15/09/2018 Aircon, Electrical,
• 22/09/2018 Water Tank
• 29/09/2018 Robes, Showers
• 05/10/2018 Main floor tiling
• 13/10/2018 Door handles locks
• 17/10/2018 Fence removed
• 26/10/2018 Stairs, Features
• 03/11/2018 Driveway
• 10/11/2018 L'scaping leveling
• 14/11/2018 PCI
• 25/11/2018 Paint touch up
• 02/12/2018 Final clean up
• 07/12/2018 OCA
• 14/12/2018 Handover!
• 15/12/2018 Move in!