Were building at Elara
Marsden Park NSW

TimeLine

•             24/01/2016         $2000, initial H&L deposit - W

•             27/01/2016         $1000, Initial land deposit

•             31/01/2016         W Changed the package to house only

•             4/02/2016           W Request for new tender

•             7/02/2016           $1000 Initial H deposit & request for M tender

•             15/02/2016         5% Land deposit

•             11/04/2016         $350 W Penalty and request for 2nd tender

•             1/06/2016           Land stamp duty

•             7/06/2016           $4000 Deposit for W builder, cancel M builder

•             24/06/2016         Tiling, Air-con, Kitchen

•             6/07/2016          Wall Unit, Media Entertainment Units

•             8/07/2016           Outdoor and Porch Tiling

•             13/09/2016         Landscape Plan

•             22/09/2016         Air Conditioning Upgrade

•             23/09/2016         Electrical Plan

•             26/09/2016         Post Contract Variations, Balance of 5% Deposit

•             25/09/2016         PA for Full Landscaping Plan

•             21/02/2017         Construction Update

•             26/02/2017         First sight to the land and street

•             15/03/2017         Revised Landscape Quotation

•             16/03/2017         Land ready for valuation

•             17/03/2017         Bank’s conditionally approved

•             27/04/2017         Registered Land

•             19/05/2017         Starting of preparation of council's plan & lodging

•             17/05/2017         We own the lot

•             09/06/2017         Contour Survey Report

•             15/06/2017         Bore Hole Report

•             17/08/2017         Council Development Approval

•             17/08/2017         Construction Certificate

•             25/08/2017         Lender’s Construction Loan Policy Changed (from 5% to 10% deposit)

 

•             27/08/2017         Found the structural error, builder re-apply of construction plan to the Council

•             31/08/2017         1st Blacktown Council Rates and Charges

•             01/09/2017         Final Ground Floor Electrical Plan and Variation completed

•             15/09/2017         1st Electricity and Gas Bills

•             15/09/2017         Section 96 Approved by the Council

•             27/09/2017         Final Colour Selection and Variation Completed

•             29/09/2017         Water Board Approval Sewer Peg Out, $910

•             15/11/2017         Final measure in the Laundry room, received variation but declined payment

•             27/11/2017         Received the final End Panel from builder

•             07/12/2017        Clear the site, no long grass and clean, send photo to the builder

•             16/01/2018         Construction or 2nd Loan Approved!

•             17/01/2018         Day was not good, received new variation charge

•             24/01/2018         Agreed to pay the new variation - $7K contract expiry

•             25/01/2018         Paid additional 5% to the builder to avoid paying LMI to bank

•             30/01/2018         Progress to the Production Estimate Department​

•             04/02/2018         Site started!!!

•             07/02/2018         Filling & Excavation!

•             12/02/2018         Additional piering

•             15/02/2018         Piers are done

•             21/02/2018         Slab is ticked

•             06/03/2018         Plumbing & Electrical

•             13/03/2018         External Drainage

•             14/03/2018         Windows delivered

•             27/03/2018         Lower frame 

•             29/03/2018         Upper frame 

•             05/04/2018         Frame completed

•             09/04/2018         Rough-in Plumbing

•             12/04/2018         Bricks Delivery

•             18/04/2018         Half Bricks 

•             25/04/2018         Scaffolding

•             03/05/2018         Bricks cement

•             11/05/2018 Upper-level bricks

•             17/05/2018         Bricks completed

•             24/05/2018         Roof Gutters 

•             28/05/2018         Roof completed

•             09/06/2018         Upper Acid Wash

•             15/06/2018         Rain Delay

•             22/06/2018         Facade Rendering

•             29/06/2018         Lower eaves done

•             06/07/2018         Lower eaves painting

•             13/07/2018         Internal rough in

•             20/07/2018         Speaker wiring

•             24/07/2018         Mixed fill removed

•             01/08/2018         Plasterboard

•             07/08/2018         Sliding doors

•             14/08/2018         Doors, Wet Areas

•             24/08/2018         Tiles, Cement

•             01/09/2018         Kitchen Cabinets

•             07/09/2018         Sinks & Benchtops

•             15/09/2018         Aircon, Electrical,

•             22/09/2018         Water Tank

•             29/09/2018         Robes, Showers

•             05/10/2018         Main floor tiling

•             13/10/2018         Door handles locks

•             17/10/2018         Fence removed

•             26/10/2018         Stairs, Features 

•             03/11/2018         Driveway

•             10/11/2018         L'scaping leveling 

•             14/11/2018         PCI

•             25/11/2018         Paint touch up

•             02/12/2018         Final clean up

•             07/12/2018         OCA

•             14/12/2018         Handover!

•             15/12/2018         Move in!

 

 

 