Stage 05: Some Tilings, Kitchen Cabinets and Vanities Installed
Stage 05: Week 27, Tilings on all wet areas and outdoors, Cabinets and Vanities Installed.
Week 29 from filling and scrap
This week 29 was finally the 'break ice', it is little but a progress!
My status and delay progress from 6 weeks is now downgrade to 3 weeks. My SS was able to catch up, however were expecting more :-)